San Diego, CA
Status: Completed in 2003
| Developer | Lambert Development LLC |
| General Contractor | Roel Construction, San Diego |
| Reinforcing Steel Sub-Contractor | J. L. Davidson, Santee, CA |
| Structural Engineer | KPFF, San Diego |
| Architect | Carrier Johnson |
Two 23-story Poured in Place Towers
Winner: Structural Engineers Association of California (SEAOC) 2003 Structural Engineering Excellence Award – Best Use of Conventional Techniques in New Building Construction
“The Renaissance project was a good assessment because one tower was built with BauGrid® and the other was built with conventional rebar. From a structural engineering point of view, the BauGrid® cages were far superior to the conventionally tied rebar cages.”
Geoff Warcholik, S.E., Associate, KPFF